ENEC completes test for Unit 4 at Barakah nuclear power plant

  • Date: 19-May-2020
  • Source: Gulf Business
  • Sector:Industrial
  • Country:UAE
  • Who else needs to know?

ENEC completes test for Unit 4 at Barakah nuclear power plant

ENEC is currently in the final stages of construction of units 2, 3 and 4 of the plant, while the overall construction of four units is more than 94 per cent complete. The Emirates Nuclear Energy Corporation (ENEC) has successfully completed the Cold Hydrostatic Testing (CHT) at Unit 4 of the Barakah Nuclear Energy Plant, it announced on May 19.. In March, ENEC completed the fuel assembly loading into Unit 1 of the Barakah nuclear power plant, marking the start of nuclear operations to generate electricity..