Diyar Al Muharraq announcing Jeewan Project updates

  • Date: 06-May-2020
  • Source: Bizbahrain
  • Sector:Real Estate
  • Country:Bahrain
  • Who else needs to know?

Diyar Al Muharraq announcing Jeewan Project updates

Development of the 173 villas in phase 1 commenced on the 1st of November, 2018 and has reached a completion rate of 75%, while the development of the further 119 villas in phase 2 commenced on the 15th of April, 2019 reaching a completion rate of 66%.. The construction rate of phase 3 is currently ahead of schedule, reaching a completion rate of 21% and is expected to be completed by the second quarter of 2021..