Uganda refinery FEED to complete in August
Uganda refinery FEED to complete in August
Front-end engineering and design (FEED) work on the Uganda refinery should be completed in August, with a final investment decision (FID) possible in June 2022.
The general manager for the refinery project Michael Mugerwa set out the plans during the Uganda Chamber of Mines & Petroleum's 7th Annual Oil and Gas Convention. The plant should reach commissioning in 2026.
FEED is at 97%, Mugerwa said.