Oman’s OETC preparing tenders for Phase 2 of unified electricity grid project

  • Date: 04-Apr-2023
  • Source: Zawya
  • Sector:Oil & Gas
  • Country:Oman
  • Who else needs to know?

Oman’s OETC preparing tenders for Phase 2 of unified electricity grid project

Oman Electricity Transmission Company (OETC), member of Nama Group, announced that it is preparing tenders for the second phase of Rabt project, also referred to as the North-South Interconnection Project, which aims to create a unified electricity grid in the Gulf country.

Rabt 2 involves the construction of three additional grid stations, OETC announced on its official twitter account.

“We are currently in the process of preparing for tenders that will be floated in the coming months. We are excited to move forward with this phase and continue our commitment to expanding and improving the Sultanate's power network,” the company tweeted.

OETC said Phase 1, which involves the construction of five grid stations: Nahaida GS, Barik GS, Suwaihat GS, Duqm GS, and Mahout GS, along with 400 kV transmission lines connecting the grids, has achieved 93 percent completion rate.

“We expect to finish these projects by the end of the third quarter of this year,” the company said its tweet.

Rabt aims to connect the northern and southern power grids of the Sultanate with a 400 kV Over Head Line (OHL), which is being completed in two phases.

Phase 1 aims to connect the north grid (Main Interconnected System) with the grids of Petroleum Development Oman