Oman’s Duqm Refinery now 98% complete

  • Date: 24-May-2023
  • Source: Zawya
  • Sector:Real Estate
  • Country:Oman
  • Who else needs to know?

Oman’s Duqm Refinery now 98% complete

MUSCAT: Duqm Refinery project, OQ8, has been making steady progress, with a total completion rate of 98.10% as of May 2023. The project has been a major undertaking for Oman and has been designed to enhance the country’s oil refining capabilities.

In a video update released by OQ8, as of May 2023, the project has seen 482, 857 cubic metres of concrete poured, indicating significant progress in the construction phase.

Moreover, the project has seen the installation of 6,960,453 metres of electric cable and 4,169,385 metres of instrumental cable, indicating a high level of attention to detail in ensuring the facility’s electrical systems are fully operational.

The overall commissioning progress of the Duqm Refinery project stands at 65.94% as of April 2023, highlighting that the facility is moving closer to completion.

Commissioning is a crucial phase in the project, where the various systems and processes are tested to ensure they are working correctly before the facility is fully operational. The high level of commissioning progress achieved thus far is an encouraging sign that the facility will be ready to start operations soon.

The project has also been a significant employer, with a total of 4,821 manpower on-site as of May 2023. The project has provided