Dubai awards $119.8m 132kV Substation Projects

Dubai Electricity and Water Authority (DEWA) announced in a statement that it has commissioned a new 132/11kV substations in Al Awir First with a transmission capacity of 150 MVA, at a total cost of AED 180 million.

DEWA also inaugurated a new transmission 400/132kV substation in Jebel Ali First and overhead cables with a conversion transmission of 2,000 MVA, at total cost of AED 338 million.

This raises the total number of 400 kV transmission substations in Dubai to 27 stations and the number of 132kV transmission substations to 333 stations, in addition to 30 other 132kV substations under construction.

DEWA has awarded new contracts for five 132/11 kV substations in citizen housing neighbourhoods in Wadi Al Amardi, Wadi Al Shabak, Nadd Hessa, Al Khawaneej 2, Al Awir 1, with a total cost of AED 440 million.

HE Saeed Mohammed Al Tayer, MD & CEO of DEWA, highlighted DEWA’s commitment to providing a decent life for citizens by providing the infrastructure needed to implement the integrated housing plan launched under the directives of HH Sheikh Mohammed bin Rashid Al Maktoum, Vice President and Prime Minister of the UAE and Ruler of Dubai; and by HH Sheikh Hamdan bin Mohammed bin Rashid Al Maktoum, Crown